Skip to main content

Watts Bar 2 Fuel Load is a Major Milestone

Chris Earls
The following is a guest blog post by NEI’s Chris Earls, who helped load the fuel before the startup of Watts Bar 1.

Last Friday, employees of Tennessee Valley Authority’s (TVA) Watts Bar Nuclear Plant started loading the first of 193 new fuel assemblies into its Unit 2 reactor. This action marked the first, initial core load of a commercial nuclear reactor in the U.S. in nearly two decades. When I heard this exciting news, I couldn’t help but recall some happy memories from earlier in my career when I worked on Watts Bar Unit 1.

The fuel load and startup of Watts Bar Unit 2 is a very important milestone for TVA and the nuclear industry. I was working at TVA in the late 1980’s when the startup of Watts Bar Unit 1 was one of our focus areas. In looking back, it amazes me how much work was entailed in getting the plant ready for operation. I was fortunate enough to return in the early ‘90s as a member of the Institute of Nuclear Power Operations (INPO) team that came on site to evaluate the plant’s readiness for startup (Watts Bar Unit 1 began commercial operations in June 1996) and was really impressed with how much had been accomplished. To now see that TVA has been able to successfully construct Watts Bar Unit 2 and is loading fuel is incredibly satisfying.

Initial fuel load is an exciting time at the site. It is a seminal moment where all the hard work pays off. You know that once the fuel is loaded, you’ve taken a huge step toward the goal of safely and reliably producing power. You can be certain that everyone at TVA realizes there’s still plenty of work to do. But this step energizes and motivates everyone to keep moving forward. It’s also the step that transitions the plant from traditional power plant construction and operational protocol to a nuclear power plant. The testing that will occur over the next few months will help ensure that the plant’s safety systems will perform reliably.

As the plant progresses over the next few months through initial criticality, the excitement at the plant will build and ultimately conclude with full power operation. I look forward to the day that the site and industry will justifiably celebrate this significant accomplishment.

Comments

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should